Dubai Airports to start first phase of operations at T3 from Oct 14

  • United Arab Emirates: Wednesday, August 20 - 2008 at 15:11
  • PRESS RELEASE

Dubai Airports has announced that a phased transition of operations to Dubai International's new Terminal 3 will start from October 14, 2008.

Dubai Airport Terminal 3



The 'soft' opening will be implemented in four phases, to ensure that systems and processes are working to the highest standards of efficiency, enabling customers to make their way through the facility as easily and speedily as possible.

The Emirates Airline-dedicated terminal is currently undergoing operational readiness trials to ensure that customers have an unmatched experience, whether arriving, departing or in transit.

HH Sheikh Ahmed Bin Saeed Al Maktoum, President of Dubai Civil Aviation Authority, and Chairman of Dubai Airports said:
"Terminal 3 and the associated development represent a much needed expansion of Dubai's aviation infrastructure. The new facility will play an important role in supporting Dubai's economic progress, and reaffirm the city's image as an emerging global aviation hub."


Reiterating that Terminal 3 will be made fully operational in a phased approach, Paul Griffiths, CEO of Dubai Airports, said: "Raising customer service standards at Dubai International is at the heart of our strategy. We want to make absolutely sure that all the systems and processes at Terminal 3 are working smoothly and that customers experience nothing short of world-class facilities and service when they use the new Terminal. It is precisely for this reason that we have decided to make Terminal 3 fully operational in phases."

He added: "We are also conducting a series of operational readiness trials at Terminal 3 and its airside facility as a run-up to the 'soft' opening in October."

Dubai Airports conducted the first major operational trial, involving over 2,000 volunteers, on August 9. Some 6,000 volunteers will participate in similar trials scheduled to be conducted later this month and at the end of September.

Quick facts

Terminal 3 & Associated Airside Facilities



The expansion plan of $4.5bn includes the construction of Terminal 3 and two associated airside facilities.

The expansion will cater to the rapid expansion of Emirates fleet, especially to serve its fleet of superjumbo the Airbus A380.

The two airside facilities will have 23 gates specifically designed for the super jumbo for twin deck embarking and disembarking.

The second airside facility will be dedicated to the A380 and will be ready in 2009.

Detailed A380 compatibility tests were carried out at Dubai International in August 2007.

Dubai International fulfilled all A380 compatibility tests, including those for taxiways, runway, and ground support equipment as well as docking trials at the terminal gate.

By the end of 2008, Dubai International will have a total of seven gates for superjumbo A380.

Upon completion of the ongoing expansion, Dubai International will have 25 gates for the A380, making Dubai the world's largest A380 dedicated facilities.

Every aspect of the expansion is designed for high volume passenger throughput, associated with full fledged A380 operations.

Terminal 3



Multi-level underground structure measuring 300mX350m

Built-up area of approximately 515,000 mē

Departure/Arrival halls located 20m below the apron and taxiways

220 check-in counters

14 baggage belts

Restaurants

First & Business Class lounges

2600 underground parking spaces

Terminal 3 and associated facility will have a car park for 2600 cars, there are a total of 157 elevators, 97 escalators and 82 moving walkways (travelators)

Since Terminal 3 is underground, the baggage handling system here is not only the largest such system in the world, but also the deepest

Total length of baggage belt is 90 kilometers and it will handle around 15,000 items of baggage per hour

8,000 bags per hour can be checked-in at the check-in counters

The baggage handling solution is a combination of belt and tray technology

The system can transport baggage at 7.5 metres per second

It has up to 800 RFID read/write stations for 100% accurate tracking

To eliminate disruptions, the system is designed to handle baggage larger than the norm and of indeterminate shape

T3 Associated Facility



Multi-level structure for departures, arrivals and other facilities

924m long x 80 m wide at mid point narrowing to 56m at both edges

Built up area of 670,000 mē

Total of 26 contact gates

59 passenger loading bridges

Total shopping area of 10,700m2 at Concourse 2 and 4,800 m2 at Terminal 3 (duty free shop/storage/retail offices)

5 special gates to handle A 380 Super Jumbo aircraft

300 room hotel and health club will include 5 and 3 star rooms

15,000 square meters to include Duty Free shopping and restaurants (combined with T3)

First and Business Class lounges

Automated People Movers
 
Article Options
Log in to request more information from Dubai Airports

Notes and Media Contacts »

DUBAI AIRPORTS
Dubai Airports owns and operates Dubai International and the upcoming Dubai World Central - Al Maktoum International.

DUBAI INTERNATIONAL
Connected to over 210 destinations across six continents through 123 airlines, Dubai International has grown at an unparalleled average of over 15 per cent annually since 2002. With throughput reaching 34.4 million passengers, up 19.3 per cent over 2006, Dubai International was the world's fastest growing airport in 2007 in terms of international passengers (among airports with 20 million passengers or over).

Dubai International accounts for over 27% of all passenger and aircraft movement in the Middle East and Africa region. The airport will open its new Terminal and associated airside facility in the summer of 2008 and another A380-specific facility in 2009, tripling its total capacity to 75 million PPA. Dubai expects 60 million passengers in 2010.

DUBAI WORLD CENTRAL - AL MAKTOUM INTERNATIONAL
Even as the opening of Dubai International's US$ 4.5 billion expansion draws closer, work is already in progress on a project to build the world's largest airport barely 40 kilometres away. Upon completion Dubai World Central - Al Maktoum International will have capacity to cater to 120 million passengers annually and handle 12 million tonnes of cargo at its 16 air cargo terminals.

Disclaimer »

Articles in this section are primarily provided directly by the companies appearing or PR agencies which are solely responsible for the content. The companies concerned may use the above content on their respective web sites provided they link back to http://www.ameinfo.com

Any opinions, advice, statements, offers or other information expressed in this section of the AMEinfo.com Web site are those of the authors and do not necessarily reflect the views of AME Info FZ LLC / Emap Limited. AME Info FZ LLC / Emap Limited is not responsible or liable for the content, accuracy or reliability of any material, advice, opinion or statement in this section of the AMEinfo.com Web site.

For details about submitting your stories, please read the guide - all content published is subject to our terms and conditions