Works Ministry: road 3445 revamp project 90% complete
- Bahrain: Monday, December 03 - 2012 at 13:52
- PRESS RELEASE
MoW's Roads Projects and Maintenance Director Raed Al Salah revealed that the Ministry has reached 90% completion in Road 3445 Revamp Project, and also the construction of a parking lot in Block 734 in A'Ali.
According to Al Salah, the Ministry has coordinated with the Electricity & Water Authority from the start of the project to develop a programme to transfer and divert the electricity poles carrying the overhead cables conflicting with the road and therefore preventing the contractor from completing the rest of the works.
Most works are now complete, and a programme is now in place to transfer electricity to the new network, remove the poles, complete the remaining road works and put into effect changes proposed by the Municipal Council.
Article Options
Notes and Media Contacts »
Disclaimer »
Articles in this section are primarily provided directly by the companies appearing or PR agencies which are solely responsible for the content. The companies concerned may use the above content on their respective web sites provided they link back to http://www.ameinfo.com
Any opinions, advice, statements, offers or other information expressed in this section of the AMEinfo.com Web site are those of the authors and do not necessarily reflect the views of AME Info FZ LLC / 4C. AME Info FZ LLC / 4C is not responsible or liable for the content, accuracy or reliability of any material, advice, opinion or statement in this section of the AMEinfo.com Web site.
For details about submitting your stories, please read the guide - all content published is subject to our terms and conditions



Posted by Ishraq Al Tal